YALLOURN MINE ALLIANCE

Australia’s second largest open cut mine is adjacent to the Yallourn W Power Station and annually mines around 18 million tonnes of brown coal.

Pro Draft manages the Yallourn Mine onsite drawing office

We provide on-site electrical & mechanical drafting services including; 3D modelling, measuring and technical assistance .

2012 Dredger No. 12 Mid-Life Outage

  • Provided 3D Model of redesigned bucket wheel for manufacture
  • Prepared detail & arrangement drawings of re-designed bucket wheel drive shaft and associated components to facilitate new adapter sleeve assembly
  • Revised drawings for bucket wheel drive gearbox overhaul
  • Detailed drawings of new slewing head ball path for manufacture and installation

2011 New Maryvale Coal Field – Conveyor Relocations

  • Provided conceptual layouts and arrangements for new conveyors, including relocation and re-use of existing plant
  • Revised the 22kV & 6.6kV distribution system drawings
  • Provided conceptual and transitional drawings for the re-routing of existing feeders to clear new plant

Categorised in:

This post was written by admin